Humboldt, IA – Humboldt City Administrator Cole Bockelmann says paving will commence today and tomorrow along the westbound lane of Sumner Avenue in the downtown corridor.
He says that construction is estimated to wrap up by the end of August. Flooding in late June and early July along with weather were factors in some delays to the project. The total cost of the project including all three phases was $1.39 million.